Work No. 1 – as shown on sheets 1 and 2 of the works plans and being the construction of new highway comprising—

(a)

Work No. 1A

(i)

the construction of new highway comprising carriageway and cycleway and forming the new bridge northern approach;

(ii)

the construction of a new roundabout, together with related approach roads and adjacent cycleways;

(iii)

the construction of earth embankments supporting the new highway;

(iv)

the construction of a building to accommodate electrical plant and the installation of electrical apparatus; and

(v)

associated landscaping.

(b)

Work No. 1B

(i)

the construction of new highway comprising carriageway and cycleway;

(ii)

the construction of a bridge deck supporting the new highway;

(iii)

the construction of an abutment and pier supporting the new bridge deck;

(iv)

the construction of piles and pile caps supporting the abutment and pier; and

(v)

the construction of new private means of access as shown on sheet 1 of the rights of way and access plans.

(c)

Work No. 1C

(i)

the construction of new highway comprising carriageway and cycleway;

(ii)

the construction of a bridge deck supporting the new highway;

(iii)

the construction of piers supporting the new bridge deck;

(iv)

the construction of piles and pile caps supporting the piers; and

(v)

the construction of new private means of access as shown on sheet 1 of the rights of way and access plans.

(d)

Work No. 1D

(i)

the construction of new highway comprising carriageway and cycleway;

(ii)

the construction of a bridge deck supporting the new highway;

(iii)

the construction of piers within the watercourse supporting the new bridge deck;

(iv)

the construction of piles and pile caps within the watercourse supporting the piers and fendering;

(v)

the construction of an opening section of bridge and associated barriers and signage; and

(vi)

the construction of fendering within the watercourse.

(e)

Work No. 1E

(i)

the construction of new highway comprising carriageway and cycleway and forming the new bridge southern approach;

(ii)

the construction of a bridge deck supporting the new highway;

(iii)

the construction of abutments and piers supporting the new bridge deck;

(iv)

the construction of piles and pile caps supporting the abutments and piers;

(v)

the construction of earth embankment with retaining walls to support the new highway;

(vi)

the construction of new private means of access as shown on sheet 2 of the rights of way and access plans; and

(vii)

the improvement of existing highways, including realignment, to facilitate tie-ins to Work No. 2.

Notes on Schedule 1

Commencement

I1

Sch. 1 in force at 21.5.2020, see art. 1