Schedule 11 LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKENI1
England and Wales
(1) Location | (2) Number of land shown on land plans | (3) Purpose for which temporary possession may be taken | (4) Relevant part of the authorised development |
|---|---|---|---|
| City of Lancaster | 8 | Temporary working area to construct property boundary | Work No. 1(iv) |
| 9 | Temporary working area to strengthen existing bridge | Work No. 1(iii) | |
| 37 | Temporary working area to provide new access off Morecambe Road (A589); new egress onto a road connecting to Hadrian Road and to reconfigure internal circulation and car parking layout | Work Nos. 1(v) and (vii) | |
| 38 | Temporary working area to construct and improve the existing access | Work No. 7 | |
| 39, 40, 43, 47, 48 and 50 | Access and temporary working area to undertake accommodation works including erection of boundary fencing and gates, extending existing car parking area, construction of new access road and car parking areas and other mitigation works. | Work No. 7 | |
| 41 | Temporary working area to construct screening mound | Work No. 7 | |
| 44 | Temporary working area to demolish neighbouring buildings | Work No. 7 | |
| 67 | Temporary working area to regrade existing ground | Work No. 1(x) | |
| 82, 89, 99, 103, 116, 118, 122, 181, 197 and 207 | Storage areas for soil arising and other materials | Work Nos. 1-17 | |
| 85 | Temporary working area to construct new access | Work No. 1(xiii) | |
| 89a | Temporary working area to lay down beams and other associated materials and to erect cranes in connection with the construction of the new railway bridge on adjoining land | Work No. 1(xiii) | |
| 93 | Temporary working area in connection with the construction of the new railway bridge | Work No. 1(xiii) | |
| 100 | Temporary working area to construct new access | Work No. 1(xiii) | |
| 102, 104, 105, 106 , 107, 113 and 115 | Temporary working area in connection with the construction of the new canal bridge including construction and maintenance of a temporary bridge over the canal and connection of new footpath and cycle track to canal towpath | Work Nos. 1(xiv) and (xv) | |
| 120 | Temporary working area to construct and maintain temporary diversion of Lancaster Road (A6) and to regrade land upon removal of temporary diversion | Work No. 1(xvii) | |
| 121 | Storage areas for soil arising and to regrade land upon removal soil arising | Work No. 1(xvii) | |
| 125, 127 and 128 | Temporary working area on part of Beaumont Gate Farm to regrade existing ground to new level of Lancaster Road (A6) and to improve existing accesses off the stopped up section of Lancaster Road (A6) | Work No. 1(xvii) | |
| 129, 131, 133 and 134 | Temporary working area in connection with the construction of the new farm occupation bridge and access track, including regrading land | Work No. 9 | |
| 139, 142 to 173 | Temporary working area | Work No. 5 | |
| 140 and 141 | Temporary right of access | Work No. 5 | |
| 180 | Temporary working area to regrade existing ground to new level of Green Lane | Work No. 1(xix) | |
| 182, 184, 185 and 186 | Temporary working area to regrade and divert watercourse known as How Gill Brook | Work Nos. 1(xx) and 4 | |
| 183, 189, 190, 192 and 192a | Temporary working area to construct and maintain temporary diversion of Kellet Lane and to regrade existing ground to new level of Kellet Lane | Work No. 1(xxi) | |
| 192b, 193, 194 and 196 | temporary working area | Work No. 1(xxii) | |
| 211 and 212 | Temporary working area to regrade watercourse known as Cote Beck | Work No. 1(xxiii) | |
| 217 | Temporary working area to construct and reconfigure existing main access and entrance gate to Halton Training Camp off Halton Road | Work No. 8 | |
| 218 | Compounds and ancillary features | Work Nos. 1-17 | |
| 227, 231, 232, 234 and 236 | Temporary working area to construct the new bridge over the River Lune, to lay down beams and other associated materials, erect cranes and to construct a footpath and cycle track forming part of the Lancaster to Caton Cycle Track – River Lune Cycleway (No. 69) and River Lune Millennium Path | Work No. 1(xxvi) | |
| 240 | Temporary working area to construct and improve the existing access to the hotel known as Holiday Inn Lancaster | Work No. 1(xxix) | |
| 241 | Temporary right of access along access way to the west of the hotel known as Holiday Inn Lancaster | Work Nos. 1(xxvi) and (xxix) | |
| 242 | Temporary right of access along land (former railway), public footpath (No. 15) and the Lancaster to Caton Cycle Track – River Lune Cycleway (No. 69) and River Lune Millennium Path, Lune Valley Ramble, the Caton Trail and Halton Circular Walk | Work No. 1(xxix) | |
| 261 | Temporary working area to construct access track and fence for the premises known as Cuckoo Farm or Ridge Farm | Work No. 1(xxviii) | |
| 262, 264 and 266 | Temporary working area to erect retaining wall and to construct new access off Caton Road (A683), and to regrade existing ground, for the property known as Hudson’s Farm | Work Nos. 1(xxviii) and (xxxi) | |
| 267, 268 and 269 | Temporary working area to improve the existing access off Caton Road (A683) for the properties known as Tarn View and Three Acres | Work No. 1(xxx) | |
| 271 | Temporary working area to construct access track, regrade existing ground, and install drainage | Work No. 1(xxx) | |
| 275, 277 and 278 | Temporary working area to realign Grimeshaw Lane | Work No. 1(xxxiv) | |
| 280, 283, 285 and 287 | Temporary working area to construct foundations and erect new sign gantry | Work No. 1(xxxii) |