The Lancashire County Council (Torrisholme to the M6 Link (A683 Completion of Heysham to M6 Link Road)) Order 2013
S.I. 2013/675 · Made 19 March 2013 · Extends to England and Wales
Infrastructure Planning
Made 19th March 2013
Coming into force 9th April 2013
The application was examined by a single Commissioner (appointed by the Chair of the Infrastructure Planning Commission) in accordance with Chapter 4 of Part 6 of the 2008 Act, and the Infrastructure Planning (Examination Procedure) Rules 2010f3.
The Commissioner, having considered the representations made and not withdrawn and the application together with accompanying documents, in accordance with section 83 of the 2008 Act, has submitted a report to the Secretary of State.
The Secretary of State, having considered the representations made and not withdrawn, and the report of the Commissioner, has decided to make an Order granting development consent for the development described in the application and consent for ancillary works with modifications which, in the opinion of the Secretary of State, do not make any substantial change to the proposals comprised in the application.
The Secretary of State, in exercise of the powers conferred by sections 114, 115, 120 and 122 of, and paragraphs 1 to 3, 10 to 17, 19, 20, 23, 24, 26, 36 and 37 of Part 1 of Schedule 5 to, the 2008 Act, makes the following Order—
Annotations to the whole text
Footnotes
- f1
- f2
- f3
Contents
- Part 1: PRELIMINARY
- 1Citation and commencement
- 2Interpretation
- Part 2: PRINCIPAL POWERS
- 3Development consent etc. granted by the Order
- 4Maintenance of authorised development
- 5Limits of deviation
- 6Benefit of Order
- 7Consent to transfer benefit of Order
- Part 3: STREETS
- 8Power to alter layout etc. of streets
- 9Street works
- 10Construction and maintenance of new or altered streets
- 11Classification of roads
- 12Stopping up of streets
- 13Temporary prohibition or restriction of use of streets
- 14Access to and from works
- 15Agreements with street authorities
- Part 4: SUPPLEMENTAL POWERS
- 16Discharge of water
- 17Protective work to buildings
- 18Temporary closure of, and works in, the canal
- 19Authority to survey and investigate land
- Part 5: POWERS OF ACQUISITION
- 20Compulsory acquisition of land
- 21Time limit for exercise of authority to acquire land compulsorily
- 22Compulsory acquisition of rights
- 23Private rights
- 24Application of the Compulsory Purchase (Vesting Declarations) Act 1981
- 25Acquisition of subsoil or air-space only
- 26Acquisition of part of certain properties
- 27Rights under or over streets
- 28Temporary use of land for carrying out the authorised development
- 29Temporary use of land for maintaining authorised development
- 30Special category land
- 31Statutory undertakers
- 32Apparatus and rights of statutory undertakers in stopped up streets
- 33Recovery of costs of new connections
- Part 6: OPERATIONS
- 34Felling or lopping trees
- 35Trees subject to tree preservation order
- Part 7: MISCELLANEOUS AND GENERAL
- 36Application of landlord and tenant law
- 37Operational land for purposes of the 1990 Act
- 38Defence to proceedings in respect of statutory nuisance
- 39Protection of interests
- 40Certification of plans, etc.
- 41Service of notices
- 42Arbitration
- Signature
- Schedule 1: AUTHORISED DEVELOPMENT
- In the City of Lancaster—
- Schedule 2: REQUIREMENTS
- 1Interpretation
- 2Time limits
- 3Commencement
- 4Implementation
- 5Landscape and ecology
- 6Contaminated land
- 7Construction environmental management plan
- 8Noise and vibration
- 9Access by construction traffic
- 10Highway approvals and complementary measures
- 11Building and construction materials - highways
- 12Building and construction materials - structures
- 13Street lighting
- 14Soil
- 15Hours of working
- 16Dust and mud during construction
- 17Safeguarding of watercourses and drainage
- 18Archaeology
- 19Cultural heritage
- 20Landscaping and management of tree and hedge planting
- 21Requirements relating to Lancaster and Morecambe College
- 22Highway safety measures
- 23Gas Main Diversion
- Schedule 3: STREETS SUBJECT TO ALTERATION OF LAYOUT
- 1STREETS SUBJECT TO TEMPORARY ALTERATION OF LAYOUT
- 2STREETS SUBJECT TO PERMANENT ALTERATION OF LAYOUT
- Schedule 4STREETS SUBJECT TO STREET WORKS
- Schedule 5: SPECIAL ROADS
- 1In the City of Lancaster—
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- Schedule 6: STREETS TO BE STOPPED UP
- 1STREETS FOR WHICH A SUBSTITUTE IS TO BE PROVIDED
- 2PRIVATE ACCESSES FOR WHICH A SUBSTITUTE IS TO BE PROVIDED
- 3STREETS FOR WHICH NO SUBSTITUTE IS TO BE PROVIDED
- 4PRIVATE ACCESSES FOR WHICH NO SUBSTITUTE IS TO BE PROVIDED
- Schedule 7TEMPORARY PROHIBITION OR RESTRICTION OF USE OF STREETS
- Schedule 8: ACCESS TO AND FROM WORKS
- 1PUBLIC ACCESS TO AND FROM WORKS
- 2PRIVATE ACCESS TO AND FROM WORKS
- Schedule 9LAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED
- Schedule 10: MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
- Compensation enactments
- 1Paragraph 1
- 2Paragraph 2
- Application of the 1965 Act
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- Schedule 11LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
- Schedule 12TREES SUBJECT TO TREE PRESERVATION ORDERS
- Schedule 13: FOR THE PROTECTION OF THE CANAL & RIVER TRUST
- Interpretation
- 1Paragraph 1
- Powers requiring Canal & River Trust consent
- 2Paragraph 2
- Vehicles, plant and machinery
- 3Paragraph 3
- Fencing
- 4Paragraph 4
- Survey of waterway
- 5Paragraph 5
- Approval of plans, protective works etc.
- 6Paragraph 6
- Design of works
- 7Paragraph 7
- Notice of works
- 8Paragraph 8
- Lighting
- 9Paragraph 9
- Construction of specified works
- 10Paragraph 10
- Prevention of pollution
- 11Paragraph 11
- Access to work: provision of information
- 12Paragraph 12
- Alterations to waterway
- 13Paragraph 13
- Maintenance of works
- 14Paragraph 14
- Repayment of Canal & River Trust fees, etc.
- 15Paragraph 15
- Costs of alterations, etc.
- 16Paragraph 16
- Making good of detriment; compensation and indemnity, etc.
- 17Paragraph 17
- Details of capitalised sums to be provided
- 18Paragraph 18
- Arbitration
- 19Paragraph 19
- Explanatory note