Paragraph 7 Construction environmental management planI1

England and Wales

(1)

No part of the authorised development is to commence until a written construction environmental management plan has been submitted to and approved in writing by the relevant planning authority.

(2)

The construction environmental management plan must include measures to address—

(a)

generation of dust arising during the construction period;

(b)

the monitoring of PM10 particulates, including the taking of appropriate mitigation measures if National Air Quality Strategy objectives are exceeded or are predicted to be exceeded;

(c)

the routeing of construction vehicles during the construction phase; and

(d)

vibration.

(3)

The construction of the development must be carried out in accordance with the approved construction environmental management plan.

Annotations

Commencement

I1

Sch. 2 para. 7 in force at 9.4.2013, see art. 1