Paragraph 14 SoilI1
England and Wales
All soil must be removed from any part of the Order land that is to be excavated or traversed by heavy vehicles, plant or machinery; or where roads, buildings, plant yards or stores are to be constructed on it, and all such soil must be stored on the site for use in the restoration of the site.
No movement of soil is to occur during the inclusive period between 1 November in any year and 1 March in the following year without the prior written consent of the relevant planning authority, and at all times the stripping, movement and redistribution of soil must be restricted to times when the soil is dry and friable and the ground is sufficiently dry to allow the passage of heavy vehicles, plant and machinery over it without damage to the soil.
No soil is to be sold or otherwise removed from the Order land without the prior written consent of the relevant planning authority.
Annotations
Commencement
- I1
Sch. 2 para. 14 in force at 9.4.2013, see art. 1