OpenLegislation

Paragraph 16 Dust and mud during constructionI1

England and Wales

(1)

No part of the authorised development is to commence until wheel cleaning facilities have been installed, the design, specification and locations of which must first be submitted in writing to, and approved in writing by, the relevant planning authority.

(2)

These facilities must remain in position and be maintained in full working order and be used by all heavy goods vehicles throughout the construction of the authorised development to minimise the risk that dust, mud or other deleterious matter is transferred to the public highway by vehicles leaving the authorised development.

(3)

Measures must be taken during road construction operations to minimise the risk that dust or windblown material is carried on to adjacent property and in particular must include the watering of all haul and access roads and the spraying of storage heaps or operational construction areas as necessary during dry weather conditions.

(4)

All heavy goods vehicles carrying materials in to or out of the authorised development during the construction of the development must be securely sheeted unless the load is otherwise enclosed.

Annotations

Commencement

I1

Sch. 2 para. 16 in force at 9.4.2013, see art. 1