Article 4 Power to construct and maintain worksI1

England and Wales

(1)

The undertaker may construct and maintain the scheduled work.

(2)

Subject to article 6 (power to deviate), the scheduled work may only be constructed in the lines or situations shown on the works plans and in accordance with the levels shown on the sections.

Annotations

Commencement

I1

Art. 4 in force at 27.8.2010, see art. 1(1)