Article 50 Certification of documents, etc.I1
England and Wales
As soon as practicable after the making of this Order the undertaker must submit copies of each of the plans and documents set out in Schedule 9 (documents to be certified) to the Secretary of State for certification that they are true copies of those plans and documents.
Where any plan or document set out in Schedule 9 requires to be amended to reflect the terms of the Secretary of State’s decision to make the Order, that plan or document in the form amended to the Secretary of State’s satisfaction is the version of the plan or document required to be certified under paragraph (1).
Notwithstanding paragraph (2), the Secretary of State expects the undertaker to provide an updated F1green controlled growth framework so that this document—
F2consistently refers to “within six months of new legal limits being published”; and
reflects the revised control needed to take account of F3paragraph 29 (annual air traffic movement cap for the authorised development) in Schedule 2 (requirements) which secure an annual movement limit of 209,410 movements.
A plan or document so certified will be admissible in any proceedings as evidence of the contents of the document of which it is a copy.
Annotations
Textual amendments
- F1
Words in art. 50(3) substituted (21.3.2026) by The London Luton Airport Expansion Development Consent (Correction) Order 2026 (S.I. 2026/328), art. 1, Sch.
- F2
Word in art. 50(3)(a) substituted (21.3.2026) by The London Luton Airport Expansion Development Consent (Correction) Order 2026 (S.I. 2026/328), art. 1, Sch.
- F3
Word in art. 50(3)(b) substituted (21.3.2026) by The London Luton Airport Expansion Development Consent (Correction) Order 2026 (S.I. 2026/328), art. 1, Sch.
Commencement
- I1
Art. 50 in force at 24.4.2025, see art. 1