Paragraph 36 Off-site highway works, Work Nos. 6e(d), (e), (f), (j) and (q)I1
England and Wales
No part of the F1Offsite Highway Works, Work Nos. 6e(d), 6e(e), 6e(f), 6e(j) and 6(e)(q) may commence, until a report which provides evidence, including recent monitoring data, that the works would be required to mitigate airport-related traffic has been submitted to and approved by the relevant local highway authority in writing.
If the relevant local highway authority confirms that the works would be required to mitigate airport-related traffic then the detailed design of the works shall be F2submitted for approval and thereafter carried out under the provisions of paragraph 6 (detailed design) of Part 2 of this Schedule.
Annotations
Textual amendments
- F1
Words in Sch. 2 para. 36(1) substituted (21.3.2026) by The London Luton Airport Expansion Development Consent (Correction) Order 2026 (S.I. 2026/328), art. 1, Sch.
- F2
Words in Sch. 2 para. 36(2) substituted (21.3.2026) by The London Luton Airport Expansion Development Consent (Correction) Order 2026 (S.I. 2026/328), art. 1, Sch.
Commencement
- I1
Sch. 2 para. 36 in force at 24.4.2025, see art. 1