Paragraph 63 I1
England and Wales
(1)
Notwithstanding article 12 (construction and maintenance of new, altered or diverted streets) of this Order, but subject to sub-paragraph (2), the undertaker must maintain the specified works throughout the maintenance period to a standard appropriate to their use by the public until the final certificate is issued in accordance with paragraph 64 (final certificate).
(2)
Nothing in sub-paragraph (1) makes the undertaker responsible during the maintenance period for the maintenance of any highway, street works or maintenance works—
(a)
undertaken by any person other than the undertaker; or
(b)
which do not form part of the specified works.