OpenLegislation

Paragraph 63 I1

England and Wales

(1)

Notwithstanding article 12 (construction and maintenance of new, altered or diverted streets) of this Order, but subject to sub-paragraph (2), the undertaker must maintain the specified works throughout the maintenance period to a standard appropriate to their use by the public until the final certificate is issued in accordance with paragraph 64 (final certificate).

(2)

Nothing in sub-paragraph (1) makes the undertaker responsible during the maintenance period for the maintenance of any highway, street works or maintenance works—

(a)

undertaken by any person other than the undertaker; or

(b)

which do not form part of the specified works.

Annotations

Commencement

I1

Sch. 8 para. 63 in force at 24.4.2025, see art. 1