Paragraph 23 Fencing and other means of enclosureI1

England, Wales and Scotland

(1)

No phase of the Bulls Lodge substation works may commence until written details of all proposed temporary fences, walls or other means of enclosure (including those set out in the construction environmental management plan), for that phase have been submitted to and approved by the relevant planning authority.

(2)

No phase of the Bulls Lodge substation works may commence until written details of all permanent fences, walls or other means of enclosure for that phase (which must be substantially in accordance with the relevant outline design principles) have been submitted to and approved by the relevant planning authority.

(3)

For the purposes of sub-paragraph (1), “commence” includes any permitted preliminary works.

(4)

Any construction site must remain securely fenced in accordance with the approved details under sub-paragraph (1) at all times during construction of the Bulls Lodge substation works.

(5)

Any temporary fencing must be removed on completion of the phase of construction of the Bulls Lodge substation works for which it was used.

(6)

Any approved permanent fencing must be completed before final commissioning of the Bulls Lodge substation works.

Annotations

Commencement

I1

Sch. 2 para. 23 in force at 18.7.2023, see art. 1