OpenLegislation

Schedule 6 TEMPORARY STOPPING UP OF STREETSI1

England, Wales and Scotland

(1)

Area

(2)

Street to be temporarily stopped up

(3)

Extent of temporary stopping up

Luton Borough Council and Central Bedfordshire CouncilM1 Junction 10 RoundaboutNight-time closures of all or part of the roundabout will be required to facilitate the safe construction of the authorised development
Central Bedfordshire CouncilM1 Junction 10 Northbound Diverge Slip RoadNight-time closures will be required to facilitate the safe construction of the authorised development
M1 Junction 10 Northbound Merge Slip RoadNight-time closures will be required to facilitate the safe construction of the authorised development
Luton Borough Council and Central Bedfordshire CouncilM1 Junction 10 Southbound Diverge Slip RoadNight-time closures will be required to facilitate the safe construction of the authorised development
Central Bedfordshire CouncilM1 Junction 10 Southbound Merge Slip RoadNight-time closures will be required to facilitate the safe construction of the authorised development
Luton Borough Council and Central Bedfordshire CouncilM1 Junction 10 Southbound Diverge Dedicated Left Turn LaneShort term closures will be required to facilitate the safe construction of the authorised development
Central Bedfordshire CouncilM1 Junction 10 Southbound Merge Dedicated Left Turn LaneShort term closures will be required to facilitate the safe construction of the authorised development
Luton Borough Council and Central Bedfordshire CouncilM1 SpurNight-time closures will be required to facilitate the safe construction of the authorised development
Luton Borough CouncilM1 Junction 10a Kidney Wood RoundaboutNight-time closures of all or short term closures of part of the roundabout will be required to facilitate the safe construction of the authorised development
Luton Borough Council and Central Bedfordshire CouncilA1081 Airport WayNight-time closures will be required to facilitate the safe construction of the authorised development
Capability Green Eastbound Diverge Slip RoadNight-time closures will be required to facilitate the safe construction of the authorised development
Capability Green Westbound MergeNight-time closures will be required to facilitate the safe construction of the authorised development
A1081 London RoadShort term closures will be required to facilitate the safe construction of the authorised development.
Newlands RoadShort term closures will be required to facilitate the safe construction of the authorised development.
Luton Borough CouncilLondon RoadShort term closures will be required to facilitate the safe construction of the authorised development.
Public Footpath FP43Closure of the footpath for the duration of the works required to facilitate the safe construction of the authorised development
Newlands RoadField access to arable farmland to the north-west of the M1 Spur, north-east of Newlands Road and east of London Road, from a point on the north-eastern highway boundary of Newlands road 45 metres to the north-west of its underbridge crossing of the M1 Spur. To be stopped up during the duration of the works in order to allow the use of adjacent land for construction purposes

Annotations

Commencement

I1

Sch. 6 in force at 20.11.2013, see art. 1