OpenLegislation

Paragraph 12 Footpath passing through Haweswater underpassI1

England and Wales

(1)

No part of F1Work Nos. 5, 6, 7, 8, 10 and 11 is to commence until a scheme detailing improvements to the F2path passing through Haweswater underpass has been submitted to and approved in writing by the Secretary of State following consultation with the relevant planning authority and any statutory undertaker whose apparatus may be impacted by any proposed improvements.

(2)

The scheme prepared under sub-paragraph (1) must incorporate details of improvements to the path F3within the Order land between Heybrook Close and Parrenthorn Road which passes through the underpass, details of any lighting, a timescale for implementation and details of future maintenance.

(3)

The scheme approved under sub-paragraph (1) must be implemented in accordance with the approved details prior to F4bringing into use Work Nos. 5, 6, 7, 8, 10 and 11 and thereafter must be retained for the life of the authorised development.

Annotations

Textual amendments

F1

Words in Sch. 2 para. 12(1) substituted (16.12.2025) by The M60/M62/M66 Simister Island Interchange Development Consent (Correction) Order 2025 (S.I. 2025/1329), art. 1, Sch.

F2

Word in Sch. 2 para. 12(1) substituted (16.12.2025) by The M60/M62/M66 Simister Island Interchange Development Consent (Correction) Order 2025 (S.I. 2025/1329), art. 1, Sch.

F3

Words in Sch. 2 para. 12(2) inserted (16.12.2025) by The M60/M62/M66 Simister Island Interchange Development Consent (Correction) Order 2025 (S.I. 2025/1329), art. 1, Sch.

F4

Words in Sch. 2 para. 12(3) substituted (16.12.2025) by The M60/M62/M66 Simister Island Interchange Development Consent (Correction) Order 2025 (S.I. 2025/1329), art. 1, Sch.

Commencement

I1

Sch. 2 para. 12 in force at 30.9.2025, see art. 1