Paragraph 1 InterpretationI1

England and Wales

In this Schedule—

  • “both relevant planning authorities” means South Kesteven District Council and Rutland County Council each being the relevant planning authority for part of the authorised development;

  • “date of final commissioning” means in respect of each phase of the authorised development as approved under requirement 3 the date on which each phase of the authorised development commences operation by generating electricity on a commercial basis but excluding the generation of electricity during commissioning;

  • “decommissioning timing provisions” means provisions relating to the timing for decommissioning works to take place, being all of section 2.4 of the outline operational environmental management plan; and

  • “relevant highway authority” means the highway authority for the highways that are the subject of a construction traffic management plan submitted pursuant to requirement 13(1).

Annotations

Commencement

I1

Sch. 2 para. 1 in force at 3.8.2024, see art. 1