Paragraph 10 ArchaeologyI1

England and Wales

(1)

The authorised development may not commence until:

(a)

a scheme for additional trial trenching has been submitted to and approved by both relevant planning authorities, in consultation with Lincolnshire County Council and Historic England;

(b)

additional trial trenching has been carried out in accordance with the scheme approved under sub-paragraph (a); and

(c)

updates are made to the outline written scheme of investigation to account for the results of the additional trial trenching carried out and the updated outline written scheme of investigation is submitted to and approved in writing by both relevant planning authorities in consultation with Lincolnshire County Council and Historic England.

(2)

The authorised development must be carried out in accordance with the updated outline written scheme of investigation approved under sub-paragraph 1(c).

Annotations

Commencement

I1

Sch. 2 para. 10 in force at 3.8.2024, see art. 1