OpenLegislation

Paragraph 9 Surface and foul water drainageI1

England and Wales

(1)

No phase of the authorised development may commence until written details of the surface water drainage scheme and (if any) foul water drainage system (which must be substantially in accordance with the outline surface water drainage strategy) have been submitted to and approved by the local lead flood authority and the relevant planning authority for that phase or, where the phase falls within the administrative areas of both the District of South Kesteven and the County of Rutland, both relevant planning authorities and both local lead flood authorities.

(2)

The design and operation of any phase of the authorised development must be carried out and maintained in accordance with the surface water drainage scheme and (if any) foul water drainage system approved under sub-paragraph (1) for that phase.

(3)

No phase of the authorised development may commence until a water management plan (which must be substantially in accordance with the outline water management plan) been submitted to and approved by the local lead flood authority and the relevant planning authority for that phase or, where the phase falls within the administrative areas of both the District of South Kesteven and the County of Rutland, both relevant planning authorities.

(4)

The measures set out in the water management plan submitted for approval under sub-paragraph (3) must be consistent with the details submitted for approval pursuant to requirement 14(1) (soil management plan).

(5)

The construction of any phase of the authorised development must be carried out in accordance with the water management plan approved under sub-paragraph (3) for that phase.

Annotations

Commencement

I1

Sch. 2 para. 9 in force at 3.8.2024, see art. 1