Paragraph 12 Operational environmental management planI1

England and Wales

(1)

Prior to the date of final commissioning for any phase of the authorised development, an operational environmental management plan (which must be substantially in accordance with the outline operational environmental management plan and which must include the decommissioning timing provisions) for that phase must be submitted to and approved by the relevant planning authority for that phase or, where the phase falls within the administrative areas of both the District of South Kesteven and the County of Rutland, both relevant planning authorities, such approval to be in consultation with the Environment Agency and Lincolnshire County Council.

(2)

The operational environmental management plan must include details of road routes to and from the site for any heavy goods vehicles required during operation.

(3)

The operation of any phase of the authorised development must be carried out and maintained in accordance with the approved operational environmental management plan for that phase.

Annotations

Commencement

I1

Sch. 2 para. 12 in force at 3.8.2024, see art. 1