Paragraph 36 F1
Regardless of the temporary alteration, diversion or restriction of use of any street or public right of way under the powers of article 13 (temporary prohibition or restriction of use of streets and public rights of way), EPN is at liberty at all times to take all necessary access across any such restricted, altered or diverted street or public right of way and to execute and do all such works and things in, upon or under any such street or public right of way as may be reasonably necessary or desirable to enable it to maintain any apparatus which at the time of the restriction, alteration or diversion was in that street or public right of way.
Annotations
Textual amendments
- F1
Sch. 11 Pt. 4 substituted (8.11.2024) by The Medworth Energy from Waste Combined Heat and Power Facility (Correction) Order 2024 (S.I. 2024/1136), art. 1(2), Sch. 2