The Medworth Energy from Waste Combined Heat and Power Facility Order 2024
S.I. 2024/230 · Made 20 February 2024 · Extends to England, Wales and Scotland
Infrastructure Planning
Made 20th February 2024
Coming into force 13th March 2024
The application has been examined by the Examining Authority appointed by the Secretary of State pursuant to Chapter 2 of Part 6 of the 2008 Act and in accordance with Chapter 4 of Part 6 of the 2008 Act and the Infrastructure Planning (Examination Procedure) Rules 2010f3. The Examining Authority has submitted a report and recommendation to the Secretary of State under section 74M1 of the 2008 Act.
The Secretary of State has considered the report and recommendation of the Examining Authority, has taken into account the environmental information in accordance with regulation 4 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017f4 and has had regard to the documents and matters referred to in section 104(2)f5 of the 2008 Act.
The Secretary of State, having decided the application, has determined to make an Order granting development consent for the development described in the application on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.
In accordance with section 127 of the 2008 Actf6, the Secretary of State has applied the relevant tests and is satisfied that they have been met.
Accordingly, the Secretary of State, in exercise of the powers in sections 114, 115, 120, 122, 123 and 140 of the 2008 Act, makes the following Order—
Annotations to the whole text
Marginal citations
- M1
2008 c. 29. Section 74 was amended by the Localism Act 2011 (c. 20) section 240(2), Schedule 13 [paragraph 29] and Schedule 25 Part 20. [Editorial note: words in footnote substituted (8.11.2024) by The Medworth Energy from Waste Combined Heat and Power Facility (Correction) Order 2024 (S.I. 2024/1136), art. 1(2), Sch. 1]
Footnotes
- f1
-
2008 c. 29. The relevant provisions of the 2008 Act are amended by section 137(5) of, and Schedule 13 to, the Localism Act 2011 (c. 20).
- f2
-
S.I. 2009/2264, amended by S.I. 2010/439, S.I. 2010/602, S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, S.I. 2013/522, S.I. 2013/755, S.I. 2014/469, S.I. 2014/2381, S.I. 2015/377, S.I. 2015/1682, S.I. 2017/524, S.I. 2017/572, S.I. 2018/378 and S.I. 2019/734
- f3
-
S.I. 2010/103, amended by S.I. 2012/635.
- f4
- f5
-
Section 104 was amended by section 58(5) of the Marine and Coastal Access Act 2009 (c. 23) and by section 240(2) and Schedule 13, paragraph 49(1) to (6) of the Localism Act 2011 (c. 20).
- f6
-
2008 c. 29. Section 127 was amended by sections 23(2)(a), 23(2)(b) and 23(2)(c) of the Growth and Infrastructure Act 2013 (c. 27) and by paragraph 64(2) of Schedule 13 paragraph 64(2) of the Localism Act 2011 (c. 20).
Contents
- Part 1: PRELIMINARY
- 1Citation and commencement
- 2Interpretation
- Part 2: PRINCIPAL POWERS
- 3Development consent granted by the Order
- 4Maintenance of authorised development
- 5Operation of the authorised development
- 6Disapplication of legislative provisions
- 7Benefit of this Order
- 8Consent to transfer benefit of the Order
- 9Security in respect of payment of compensation
- Part 3: STREETS
- 10Street works
- 11Power to alter layout, etc., of streets
- 12Construction and maintenance of new or altered means of access
- 13Temporary prohibition or restriction of use of streets and public rights of way
- 14Use of private roads
- 15Access to works
- 16Agreements with street authorities
- 17Traffic regulation measures
- Part 4: SUPPLEMENTARY POWERS
- 18Discharge of water
- 19Authority to survey and investigate the land
- 20Protective works to buildings
- 21Felling or lopping of trees
- 22Removal of human remains
- Part 5: POWERS OF ACQUISITION AND POSSESSION OF LAND
- 23Compulsory acquisition of land
- 24Time limit for exercise of authority to acquire land compulsorily
- 25Compulsory acquisition of rights and imposition of restrictive covenants
- 26Acquisition of subsoil only
- 27Private rights
- 28Power to override easements and other rights
- 29Application of the 1981 Act
- 30Modification of Part 1 of the Compulsory Purchase Act 1965
- 31Rights under or over streets
- 32Temporary use of land for the carrying out of the authorised development
- 33Temporary use of land for maintaining the authorised development
- 34Statutory undertakers
- 35Apparatus and rights of statutory undertakers in altered or closed streets
- 36Recovery of costs of new connections
- Part 6: MISCELLANEOUS AND GENERAL
- 37Electronic communications
- 38Application of landlord and tenant law
- 39Operational land for the purposes of the 1990 Act
- 40Defence to proceedings in respect of statutory nuisance
- 41Protective provisions
- 42Certification of plans etc.
- 43Service of notices
- 44Procedure in relation to certain approvals etc.
- 45No double recovery
- 46Arbitration
- 47Incorporation of the mineral code
- 48Modification of the section 106 agreement relating to land
- Signature
- Schedule 1: AUTHORISED DEVELOPMENT
- 1Authorised Development
- Schedule 2: REQUIREMENTS
- 1Time limits
- 2Detailed design approval
- 3Parameters of authorised development
- 4Biodiversity and landscape mitigation
- 5Landscape and ecology management plan
- 6Biodiversity net gain
- 7Highway works
- 8Drainage strategy
- 9Contamination and groundwater
- 10Construction environmental management plan
- 11Construction traffic management plan
- 12Operational traffic management plan
- 13Flood emergency management plan
- 14Waste hierarchy scheme
- 15Operational travel plan
- 16Odour management plan
- 17Fire prevention plan
- 18Lighting strategy
- 19Noise management
- 20Notice of start of commissioning and notice of date of final commissioning
- 21Employment and skills strategy
- 22Carbon capture and export readiness reserve space
- 23Carbon capture readiness monitoring report
- 24Community liaison manager
- 25Combined heat and power
- 26Air safety
- 27Local air quality monitoring strategy
- 28Decommissioning
- 29Origin of waste
- 30Amendments to approved details
- Schedule 3STREETS SUBJECT TO STREET WORKS
- Schedule 4STREETS SUBJECT TO PERMANENT ALTERATION OF LAYOUT
- Schedule 5STREETS SUBJECT TO TEMPORARY ALTERATION OF LAYOUT
- Schedule 6: ACCESS
- 1THOSE PARTS OF THE ACCESS TO BE MAINTAINED AT THE PUBLIC EXPENSE
- 2THOSE PARTS OF THE ACCESS TO BE MAINTAINED BY THE STREET AUTHORITY
- 3THOSE WORKS TO RESTORE THE TEMPORARY ACCESSES WHICH WILL BE MAINTAINED BY THE STREET AUTHORITY
- Schedule 7TEMPORARY PROHIBITION OR RESTRICTION OF THE USE OF STREETS OR PUBLIC RIGHTS OF WAY
- Schedule 8LAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED
- Schedule 9: MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS AND IMPOSITION OF NEW RESTRICTIVE COVENANTS
- 1Compensation enactments
- 2Compensation enactments
- 3Compensation enactments
- 4Application of Part 1 of the 1965 Act
- 5Paragraph 5
- Schedule 10LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
- Schedule 11: PROTECTIVE PROVISIONS
- Part 1: FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- 11Paragraph 11
- Part 2: PROTECTION FOR OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- 15Paragraph 15
- 16Paragraph 16
- Part 3: FOR THE PROTECTION OF CADENT GAS LIMITED
- 17Application
- 18Interpretation
- 19On street apparatus
- 20Apparatus of Cadent in altered or closed streets
- 21Protective works to buildings
- 22Acquisition of land
- 23Removal of apparatus
- 24Facilities and rights for alternative apparatus
- 25Retained apparatus: protection of Cadent
- 26Expenses
- 27Indemnity
- 28Enactments and agreements
- 29Co-operation
- 30Access
- 31Arbitration
- 32Notices
- Part 4: FOR THE PROTECTION OF EASTERN POWER NETWORKS
- Application
- 33Paragraph 33
- Interpretation
- 34Paragraph 34
- On street apparatus
- 35Paragraph 35
- Apparatus in restricted streets and public rights of way
- 36Paragraph 36
- Protective works to buildings
- 37Paragraph 37
- Acquisition of land
- 38Paragraph 38
- Removal of apparatus
- 39Paragraph 39
- Facilities and rights for alternative apparatus
- 40Paragraph 40
- Retained apparatus
- 41Paragraph 41
- Expenses and costs
- 42Paragraph 42
- 43Paragraph 43
- Enactments and agreements
- 43AParagraph 43A
- Cooperation
- 43BParagraph 43B
- Access
- 43CParagraph 43C
- Arbitration
- 43DParagraph 43D
- Part 5: FOR THE PROTECTION OF NATIONAL HIGHWAYS
- 44Application etc.
- 45Interpretation
- 46General
- 47General
- 48General
- 49Works outside the Order limits
- 50Prior approvals and security
- 51Construction of the specified works
- 52Payments
- 53Provisional Certificate
- 54Opening
- 55Final condition survey
- 56Defects Period
- 57Final Certificate
- 58Security
- 59Commuted sums
- 60Insurance
- 61Indemnity
- 62Maintenance of the specified works
- 63Land
- 64Expert Determination
- Part 6: FOR THE PROTECTION OF INTERNAL DRAINAGE BOARD
- 65Paragraph 65
- 66Paragraph 66
- 67Paragraph 67
- 68Paragraph 68
- 69Paragraph 69
- 70Paragraph 70
- 71Paragraph 71
- 72Paragraph 72
- 73Paragraph 73
- 74Paragraph 74
- 75Paragraph 75
- 76Paragraph 76
- Part 7: FOR THE PROTECTION OF ANGLIAN WATER
- 77Paragraph 77
- 78Paragraph 78
- 79On street apparatus
- 80Apparatus in stopped up streets
- 81Protective works to buildings
- 82Acquisition of land
- 83Removal of apparatus
- 84Facilities and rights for alternative apparatus
- 85Retained apparatus
- 86Expenses and costs
- 87Expenses and costs
- 88Cooperation
- 89Cooperation
- 90Cooperation
- 91Cooperation
- Part 8: FOR THE PROTECTION OF RAILWAY INTERESTS
- 92Paragraph 92
- 93Paragraph 93
- 94Paragraph 94
- 95Paragraph 95
- 96Paragraph 96
- 97Paragraph 97
- 98Paragraph 98
- 99Paragraph 99
- 100Paragraph 100
- 101Paragraph 101
- 102Paragraph 102
- 103Paragraph 103
- 104Paragraph 104
- 105Paragraph 105
- 106Paragraph 106
- 107Paragraph 107
- 108Paragraph 108
- 109Paragraph 109
- 110Paragraph 110
- 111Paragraph 111
- 112Paragraph 112
- 113Paragraph 113
- Part 9: FOR THE PROTECTION OF CAMBRIDGESHIRE COUNTY COUNCIL AS HIGHWAY AUTHORITY
- 114Paragraph 114
- 115Paragraph 115
- 116Paragraph 116
- 117Paragraph 117
- 118Paragraph 118
- 119Paragraph 119
- 120Paragraph 120
- 121Paragraph 121
- 122Paragraph 122
- 123Paragraph 123
- 124Paragraph 124
- 125Paragraph 125
- 126Paragraph 126
- Schedule 12: PROCEDURE FOR THE DISCHARGE OF REQUIREMENTS
- 1Interpretation
- 2Applications made under requirements
- 3Further information and consultation
- 4Appeals
- Schedule 13DOCUMENTS AND PLANS TO BE CERTIFIED
- Schedule 14MAXIMUM AND MINIMUM DESIGN PARAMETERS
- Schedule 15: ARBITRATION RULES
- 1Primary objective
- 2Time periods
- 3Timetable
- 4Procedure
- 5Arbitrator’s powers
- 6Costs
- 7Confidentiality
- Explanatory note