Paragraph 2 Applications made under requirementsI1

England, Wales and Scotland

(1)

Where an application has been made to the relevant authority for any consent, agreement or approval required by a requirement (including consent, agreement or approval in respect of part of a requirement) the relevant authority must give notice to the undertaker of their decision on the application within a period of 12 weeks beginning with—

(a)

the day immediately following that on which the application is received by the authority;

(b)

the day immediately following that on which further information has been supplied by the undertaker under sub-paragraph (2); or

(c)

such longer period as may be agreed in writing by the undertaker and the relevant authority,

whichever is the latest.

(2)

Subject to F1sub-paragraph (4), in the event that the relevant authority does not determine an application within the period set out in sub-paragraph (1), the relevant authority is to be taken to have granted all parts of the application (without any condition or qualification) at the end of that period.

(3)

Any application made to the F2relevant authority pursuant to sub-paragraph (1) mustF3—

(a)

include a statement to confirm whether it is likely that the subject matter of the application will give rise to any materially new or materially different environmental effects compared to those in the environmental statement and if it will then it must be accompanied by information setting out what those effects are; and

(b)

include confirmation that the application has been notified and provided to the requirement consultees in accordance with sub-paragraph (5), if the provision governing or requiring the application specifies that consultation with a requirement consultee is required. Such confirmation to include contact details for the requirement consultees.

(4)

Where an application has been made to the relevant authority for any consent, agreement or approval required by a requirement included in this Order, and—

(a)

the relevant authority does not determine the application within the period set out in sub‑paragraph (1) and such application is accompanied by a report pursuant to F4sub-paragraph (3) which states that the subject matter of such application is likely to give rise to any materially new or materially different environmental effects compared to those in the environmental statement; or

(b)

the F5relevant authority determines during the period set out in sub-paragraph (1) that it considers that the subject matter of such application will give rise to any materially new or materially different environmental effects compared to those in the environmental statement,

then the application is to be taken to have been refused by the relevant authority at the end of that period.

(5)

At the same time as submitting an application to the F6relevant authority for any consent, agreement or approval required by a requirement, the undertaker must also give notice of such application, and provide a copy of the application, to any requirement consultee, if the provision governing or requiring the application specifies that consultation with a requirement consultee is required. As part of the notification to any requirement consultee, the undertaker must include a statement that refers toF7—

(a)

the timeframes in which the requirement consultee can request any further information from the undertaker (via the F8relevant authority) as prescribed in paragraph 3(6)(a) and the consequences of the failure to meet those timescales as prescribed in paragraph 3(6)(b); and

(b)

the timeframes in which the requirement consultee must give notice to the F9relevant authority of its comments on the application as prescribed in paragraph 3(6)(d) and the consequences of the failure to meet those timescales as prescribed in paragraph 3(6)(e).

Annotations

Textual amendments

F1

Words in Sch. 12 para. 2(2) substituted (8.11.2024) by The Medworth Energy from Waste Combined Heat and Power Facility (Correction) Order 2024 (S.I. 2024/1136), art. 1(2), Sch. 1

F2

Words in Sch. 12 para. 2(3) substituted (8.11.2024) by The Medworth Energy from Waste Combined Heat and Power Facility (Correction) Order 2024 (S.I. 2024/1136), art. 1(2), Sch. 1

F3

Sch. 12 para. 2(3): punctuation substituted (8.11.2024) by The Medworth Energy from Waste Combined Heat and Power Facility (Correction) Order 2024 (S.I. 2024/1136), art. 1(2), Sch. 1

F4

Word in Sch. 12 para. 2(4)(a) substituted (8.11.2024) by The Medworth Energy from Waste Combined Heat and Power Facility (Correction) Order 2024 (S.I. 2024/1136), art. 1(2), Sch. 1

F5

Words in Sch. 12 para. 2(4)(b) substituted (8.11.2024) by The Medworth Energy from Waste Combined Heat and Power Facility (Correction) Order 2024 (S.I. 2024/1136), art. 1(2), Sch. 1

F6

Words in Sch. 12 para. 2(5) substituted (8.11.2024) by The Medworth Energy from Waste Combined Heat and Power Facility (Correction) Order 2024 (S.I. 2024/1136), art. 1(2), Sch. 1

F7

Sch. 12 para. 2(5): punctuation substituted (8.11.2024) by The Medworth Energy from Waste Combined Heat and Power Facility (Correction) Order 2024 (S.I. 2024/1136), art. 1(2), Sch. 1

F8

Words in Sch. 12 para. 2(5)(a) substituted (8.11.2024) by The Medworth Energy from Waste Combined Heat and Power Facility (Correction) Order 2024 (S.I. 2024/1136), art. 1(2), Sch. 1

F9

Words in Sch. 12 para. 2(5)(b) substituted (8.11.2024) by The Medworth Energy from Waste Combined Heat and Power Facility (Correction) Order 2024 (S.I. 2024/1136), art. 1(2), Sch. 1

Commencement

I1

Sch. 12 para. 2 in force at 13.3.2024, see art. 1