Paragraph 72 I1
England, Wales and Scotland
Without limiting the other provisions of this Part, the undertaker must compensate the Board in respect of all claims, demands, proceedings, costs, damages, expenses or loss that may be made or taken against, reasonably recovered from or incurred by the Board by reason of—
any damage to any drainage work so as to impair its efficiency for the purposes of flood defence;
any raising or lowering of the water table in land adjoining the authorised development or any sewers, drains and watercourses; or
any flooding or increased flooding of any such land
which is caused by, or results from, the construction of the specified work or any act or omission of the undertaker, its contractors, agents or employees whilst engaged upon the specified work.
The Board must give to the undertaker reasonable notice of any such claim or demand, and no settlement or compromise may be made without the agreement of the undertaker which agreement must not be unreasonably withheld or delayed.
The Board must use its reasonable endeavours to mitigate in whole or in part and to minimise any claims, demands, proceedings, costs, damages, expenses or loss to which this paragraph applies.
Annotations
Commencement
- I1
Sch. 11 para. 72 in force at 13.3.2024, see art. 1