Paragraph 19 Noise managementI1
England, Wales and Scotland
No part of Work No. 4A may commence until the residential use at plot numbers 11/4a and 11/4b shown on the land plans and described in the book of reference has ceased unless otherwise agreed by the relevant planning authority.
Plot numbers 11/4a and 11/4b shown on the land plans and described in the book of reference must not be used for residential purposes until the authorised development has been decommissioned in accordance with requirement 28 unless otherwise agreed by the relevant planning authority.
No part of Work No. 4A may commence until Work No. 10 has been constructed. Work No. 10 must be maintained until the authorised development has been decommissioned in accordance with requirement 28 unless otherwise agreed by the relevant planning authority.
Prior to the date of completion of commissioning of any part of Work No. 1, 1A, 2A, 2B and 9(a), an operational noise management plan for that part must be submitted to and approved by the relevant planning authority.
The operational noise management plan submitted for approval must be substantially in accordance with the outline operational noise management plan.
The relevant planning authority must consult with the Environment Agency before approving the operational noise management plan.
The operational noise management plan must be implemented as approved under sub‑paragraph (4).