Schedule 14 MAXIMUM AND MINIMUM DESIGN PARAMETERSI1
England, Wales and Scotland
Table 11
(1) Element of authorised development | (2) Work No. | (3) Maximum length (metres) | (4) Maximum width (metres) | (5) Maximum height (metres) (above finished floor level of 3.0m AOD) | (6) Minimum height (metres) (above finished floor level of 3.0m AOD) |
|---|---|---|---|---|---|
| Gatehouse / weighbridge | 2A | 9.5 | 2.4 | 3 | |
| Tipping hall | 1 | 58.5 | 38 | 18.5 | |
| Fire water tank | 2A | 16 | 10 | ||
| Fire water pump building | 2A | 12.5 | 9.5 | 5.5 | |
| Waste bunker building | 1 | 102 | 37 | 38.5 | |
| Tipping bunker | 1 | – | – | -14 | |
| Main waste bunker | 1 | – | – | -14 | |
| Boiler house building | 1 | 55 | 47.6 | 52 | |
| Loading area (a) | 1 | 12.2 | 12.2 | 12 | |
| APCr silos | 1 | 33.3 | 12.2 | 37 | |
| Loading area (b) | 1 | 12.2 | 12.2 | 12 | |
| Air pollution control building | 1 | 33.2 | 28.6 | 37 | |
| Induced draft fans building | 1 | 10 | 10 | 12 | |
| Chimneys | 1A | – | 3.2 | 90 | 84 |
| CEMS platform | 1A | – | – | 18 | |
| Switchgear building north | 1 | 35.2 | 10 | 35 | |
| Switchgear building south | 1 | 12.4 | 10 | 18 | |
| IBA enclosure east | 1 | 14 | 11 | 12 | |
| IBA enclosure west | 1 | 11 | 6 | 12 | |
| Diesel tanks and urea tanks building | 1 | 25.9 | 9.1 | 35 | |
| Compressed air station | 1 | 13 | 8 | 10 | |
| Main transformer | 2A | 11 | 6 | 12 | |
| Emergency diesel generator | 1 | 13.5 | 5.5 | 12 | |
| Air cooled condenser | 1 | 37 | 37 | 30 | |
| Turbine hall | 1 | 47 | 34 | 27 | |
| Water treatment plant | 1 | 30 | 22 | 18 | |
| Workshop and stores | 2A | 34 | 15 | 18 | |
| Administration building | 1B | 34 | 12 | 15 | |
| 132kV switching compound | 2A | 23 | 13 | 6.5 | |
| Private wire transformer | 2A | 11 | 5 | 12 | |
| Private wire switchgear compound | 2A | 7 | 6 | 12 | |
| Water re–cooling system | 1 | 18.5 | 7.5 | 27 | |
| Steam and condensate pipelines | 3 | – | – | 23 |
Annotations
Commencement
- I1
Sch. 14 in force at 13.3.2024, see art. 1