Paragraph 2 Detailed design approvalI1

England, Wales and Scotland As made

(1)

No part of Work Nos. 1, 1A, 1B, 2A, 2B, 3, 6A, 6B, 7, 8, 9 or 10 may commence until details of the layout, scale and F1, in respect of above ground development, external appearance for that Work No. have been submitted to and approved by the relevant planning authority.

(2)

The details submitted for approval under sub-paragraph (1) must be substantially in accordance with the design principles F2applicable to that work order as set out in Appendix A of the design and access statement.

(3)

Where a requirement requires the authorised development to be constructed in accordance with details approved by the relevant planning authority, the approved details are taken to include any amendments subsequently approved by the relevant planning authority.

(4)

The authorised development must be carried out in accordance with the approved details.

Annotations

Textual amendments

F1

Words in Sch. 2 para. 2(1) substituted (8.11.2024) by The Medworth Energy from Waste Combined Heat and Power Facility (Correction) Order 2024 (S.I. 2024/1136), art. 1(2), Sch. 1

F2

Words in Sch. 2 para. 2(2) inserted (8.11.2024) by The Medworth Energy from Waste Combined Heat and Power Facility (Correction) Order 2024 (S.I. 2024/1136), art. 1(2), Sch. 1

Commencement

I1

Sch. 2 para. 2 in force at 13.3.2024, see art. 1