Paragraph 2 Detailed design approvalI1
England, Wales and Scotland As made
No part of Work Nos. 1, 1A, 1B, 2A, 2B, 3, 6A, 6B, 7, 8, 9 or 10 may commence until details of the layout, scale and F1, in respect of above ground development, external appearance for that Work No. have been submitted to and approved by the relevant planning authority.
Where a requirement requires the authorised development to be constructed in accordance with details approved by the relevant planning authority, the approved details are taken to include any amendments subsequently approved by the relevant planning authority.
The authorised development must be carried out in accordance with the approved details.
Annotations
Textual amendments
- F1
Words in Sch. 2 para. 2(1) substituted (8.11.2024) by The Medworth Energy from Waste Combined Heat and Power Facility (Correction) Order 2024 (S.I. 2024/1136), art. 1(2), Sch. 1
- F2
Words in Sch. 2 para. 2(2) inserted (8.11.2024) by The Medworth Energy from Waste Combined Heat and Power Facility (Correction) Order 2024 (S.I. 2024/1136), art. 1(2), Sch. 1
Commencement
- I1
Sch. 2 para. 2 in force at 13.3.2024, see art. 1