Paragraph 20 Notice of start of commissioning and notice of date of final commissioningI1

England, Wales and Scotland As made

(1)

Notice of the commencement of commissioning of Work No. 1 must be given to the relevant planning authority within 7 days of the date on which commissioning is commenced.

(2)

Notice of the completion of commissioning of Work No. 1 must be given to the relevant planning authority within 7 days of the date on which commissioning is completed.

Annotations

Commencement

I1

Sch. 2 para. 20 in force at 13.3.2024, see art. 1