Paragraph 6 Test loads
(1)
Every repaired meter shall be tested at each of the loads specified in Table 2.
(2)
All new meters shall be calibrated and tested at a sufficient number of load points so as to ensure that meter errors are not greater than the limits specified in paragraph 9.
(3)
A test will also be carried out on new meters for starting in accordance with Test No 7 of Table 2.
(4)
The ratio accuracy shall be determined for voltage transformers that are intended for use with meters but are not tested with a meter.
(5)
Current transformers intended for use with meters but not tested with a meter shall be tested from 5% to 100% of rated current.