Paragraph 1 Pre-heatingI1
England, Wales and Scotland
(1)
The following tests shall not be carried out until the voltage circuits of meters under test and the voltage circuits of working standard integrating meters have been energised for a period of one hour or half an hour if a current of not less than either 10 per cent. of basic current or 5 per cent. of marked current is applied to the current circuits of the meters, provided that the non-registration and starting current tests may be carried out during the pre-heating period.
(2)
Sub-paragraph (1) shall not apply to a meter which the examiner is satisfied is capable of full operation as soon as it is energised.
Annotations
Commencement
- I1
Sch. 1 para. 1 in force at 1.8.1998, see reg. 1