Schedule 14 DOCUMENTS AND PLANS TO BE CERTIFIEDI1
England, Wales and Scotland
F1Table 11
| (1)Document name | (2)Document reference | (3)Revision number | (4)Date |
|---|---|---|---|
| access road visibility splay plan (contained in appendix 2.1 of appendix 12.1 of the environmental statement) | Drawing reference 31116/2001/008 | B | April 2018 |
| book of reference | 4.3 | 3 | August 2018 |
| design principles statement | 10.2 | 0 | October 2017 |
| environmental statement, Main statement | 6.1 | 0 | October 2017 |
| Appendix Volume A: 1.1 Glossary | 6.2 | 0 | October 2017 |
| Appendix Volume B: 1.2 Scoping Report and Scoping Opinion | 6.2 | 0 | October 2017 |
| Appendix Volume C: 2.6-2.14 Legislation and Policy | 6.2 | 0 | October 2017 |
| Appendix Volume D: 3.1 Mitigation Roadmap | 6.2 | 0 | October 2017 |
| Appendix Volume E: 3.2 Outline CEMP | 6.2 | 2 | July 2018 |
| Appendix Volume F: 5.1 CHP Statement | 6.2 | 0 | October 2017 |
| Appendix Volume G: 6.1-6.3 Air Quality | 6.2 | 0 | October 2017 |
| Appendix Volume H: 7.1 Noise | 6.2 | 0 | October 2017 |
| Appendix Volume H: 7.2 and 7.3 Noise | 6.2 | 1 | April 2018 |
| Appendix Volume I: 8.1-8.5 Ecology | 6.2 | 0 | October 2017 |
| Appendix Volume J: 10.1 Ground Conditions | 6.2 | 0 | October 2017 |
| Appendix Volume K: 11.1 and 11.2 LVIA | 6.2 | 0 | October 2017 |
| Appendix Volume K: 11.3 LVIA | 6.2 | 1 | April 2018 |
| Appendix Volume L: 12.1 TA (save in respect of Appendix 2.1) | 6.2 | 0 | October 2017 |
| Appendix Volume L: Appendix 2.1 of the TA | 6.2 Drawing reference 31116/2001/0008 | B | April 2018 |
| Appendix Volume M: 13.1-13.3 Historic Environment | 6.2 | 0 | October 2017 |
| Appendix Volume N: 15.1 Electric and Magnetic Fields Assessment Report | 6.2 | 0 | October 2017 |
| Figures (save in respect of Figure 11.1) | 6.3 | 0 | October 2017 |
| Figure 11.1 | 6.3 | 1 | April 2018 |
| Non-technical summary | 6.4 | 0 | October 2017 |
| the indicative site layout plans | 2.3 | 2 | June 2019 |
| land plans | 2.5 | 2 | June 2019 |
| the low level restoration scheme baseline works plan | Drawing reference: J0008128-409 | 0 | April 2018 |
| the outline construction environment management plan (contained in appendix 3.2 of the environmental statement) | 6.2 | 2 | July 2018 |
| the outline construction traffic management measures (contained in the outline construction environment management plan and appendices 5.2 to 5.5 of appendix 12.1 of the environmental statement) | 6.2 | 0 | October 2017 |
| the outline landscape and ecological mitigation and management strategy (contained in appendix 11.2 of the environmental statement) | 6.2 | 2 | June 2019 |
| the outline lighting strategy (contained in appendix 11.3 of the environmental statement) | 6.2 | 0 | October 2017 |
| the outline travel plan (contained in appendix 12.1 of the environmental statement) | 6.2 | 0 | October 2017 |
| the rights of way, streets and access plan | 2.7 | 3 | June 2019 |
| Works plans | 2.6 | 2 | June 2019 |