Paragraph 12 Control of noise during operationI1

England, Wales and Scotland

(1)

Prior to the date of final commissioning a written noise scheme providing for the control of noise generated during the operation of the authorised development must be submitted to and approved by Central Bedfordshire Council. The noise scheme must include the following:

(a)

the locations at which noise will be monitored;

(b)

the defined representative background sound level at South Pillinge Farm house;

(c)

the method of noise measurement (which must be in accord with BS 4142:2014, an equivalent successor standard or other agreed noise measurement methodology appropriate to the circumstances) and when such measurements will be carried out; and

(d)

a complaints procedure.

(2)

Except in the case of an emergency, noise (in terms of the BS 4142:2014 rating level) emitted from the operation of the authorised development must be no greater than the defined representative background sound level as approved in the noise scheme submitted pursuant to sub-paragraph (1).

(3)

The noise scheme must be carried out as approved.