Schedule 2 REQUIREMENTS
England, Wales and Scotland
- 1Time limits
- 2Detailed design approval
- 3Provision of landscaping and ecological mitigation
- 4Implementation and maintenance of landscaping and ecological mitigation measures
- 5Highway accesses
- 6Fencing and other means of site perimeter enclosure
- 7Surface and foul water drainage
- 8Contamination and groundwater
- 9Archaeology
- 10Construction Environment Management Plan
- 11Construction traffic management plan
- 12Control of noise during operation
- 13Control of noise during construction
- 14Construction hours
- 15Lighting strategy
- 16Construction Travel Plan
- 17Operating hours
- 18Decommissioning strategy
- 19Amendments to approved details
- 20Low Level Restoration Scheme
- 21Air Safety