Paragraph 7 Surface and foul water drainageI1

England, Wales and Scotland

(1)

Each of numbered works 1, 2, 3AF1... and 6 must not commence until, for that numbered work, written details of the surface and foul water drainage strategy, which shall incorporate appropriate elements of the low level restoration scheme drainage strategy where applicable, for the construction and operational phases of the authorised development have been submitted to and approved by Central Bedfordshire Council.

(2)

The surface and foul water drainage system must be constructed in accordance with the approved details before the operational phase of that part of the authorised development commences.

Annotations

Textual amendments

F1

Word in Sch. 2 para. 7(1) omitted (9.4.2020) by virtue of The Millbrook Gas Fired Generating Station (Amendment) Order 2020 (S.I. 2020/413), arts. 1, 4(4)

Commencement

I1

Sch. 2 para. 7 in force at 3.4.2019, see art. 1