Numbered work 1A(b) of the authorised development must not commence until the following details have been submitted to the Defence Geographic Centre:
(a)
the precise location of numbered work 1A(b);
(b)
the date of commencement of construction of numbered work 1A(b);
(c)
the anticipated date of completion of construction of numbered work 1A(b);
(d)
the height above ground level of the tallest structure; and
(e)
the maximum extension height of any construction equipment.