Part 1 Authorised Development

England and Wales

Work No. 3:

(a)

installation of up to four subsea cable circuits between Work No. 2 and Work No. 8 from MLWS to MHWS approximately 245 metres including cable ducts and cable crossings;

(b)

trenchless installation technique works; and

(c)

access during construction, operation, maintenance and decommissioning;

Work No. 4: access to Work No. 3 during construction;

Work No. 5: access to Work Nos. 7 and 8 during construction;

Work No. 6: access to Work No. 8 during construction;

Work No. 7: temporary laydown area of up to 800 square metres including fencing together with access to Work No. 4 during construction;

Work No. 8:

(a)

installation of up to four buried cable circuits between Work No. 3 and Work No. 9 from MHWS to the A547 approximately 142 metres including cable ducts; and

(b)

trenchless installation technique works;

Work No. 9:

(a)

installation of up to four buried cable circuits between Work No. 8 and Work No. 10 approximately 10 metres including cable ducts;

(b)

trenchless installation technique works; and

(c)

access to Work No. 10 during construction, operation, maintenance and decommissioning including works to the public highway and visibility splays;

Work No. 10:

(a)

installation of up to four buried cable circuits between Work No. 9 and Work No. 11 approximately 216 metres including cable ducts;

(b)

installation of up to four transition joint bays;

(c)

trenchless installation technique works including the creation of entry and exit pits for trenchless installation techniques and cable trenching works;

(d)

temporary construction compound of up to 30,000 square metres comprising a secondary temporary construction compound and a transition joint bay temporary construction compound;

(e)

access during construction, operation, maintenance and decommissioning;

Work No. 11:

(a)

installation of up to four buried cable circuits between Work No. 10 and Work No. 12 approximately 878 metres including cable ducts; and

(b)

trenchless installation technique works including the creation of entry and exit pits for trenchless installation techniques and cable trenching works;

Work No. 12:

(a)

installation of up to four buried cable circuits between Work No. 11 and Work No. 14 approximately 3,986 metres including cable ducts; and

(b)

trenchless installation technique works including the creation of entry and exit pits for trenchless installation techniques and cable trenching works;

Work No. 12a: access to Work No. 12 during construction;

Work No. 13: primary temporary construction compound and secondary temporary construction compound and access to Work Nos. 12 and 14 during construction including works to the public highway and visibility splays;

Work No. 14:

(a)

installation of up to four buried cable circuits between Work No. 12 and Work No. 15 approximately 2,700 metres including cable ducts; and

(b)

trenchless installation technique works including the creation of entry and exit pits for trenchless installation techniques and cable trenching works;

Work No. 15:

(a)

installation of up to four buried cable circuits between Work No. 14 and Work No. 17 approximately 2,179 metres including cable ducts; and

(b)

trenchless installation technique pit works including the creation of entry and exit pits for trenchless installation techniques and cable trenching works;

Work No. 16: primary temporary construction compound and laydown area or secondary temporary construction compound and access to Work No. 15 during construction including works to the public highway and visibility splays;

  1. 1Paragraph 1