The Mona Offshore Wind Farm Order 2025

S.I. 2025/870 · Made 4 July 2025 · Extends to England and Wales

Up to date with all changes known to legislation.gov.uk, revised to 24 October 2025.

Infrastructure Planning

Made 4th July 2025

Coming into force 28th July 2025

An application has been made to the Secretary of State under section 37 of the Planning Act 2008 f1 (“the 2008 Act”) for an Order granting development consent.

The application was examined by a panel of 5 members (appointed by the Secretary of State) in accordance with Part 6 of the 2008 Act and carried out in accordance with the Infrastructure Planning (Examination Procedure) Rules 2010f2.

The panel, having considered the representations made and not withdrawn and the application together with the accompanying documents, in accordance with section 74(2) of the 2008 Act, has submitted a report and recommendation to the Secretary of State.

The Secretary of State has considered the representations made and not withdrawn, and the report and recommendation of the panel, has taken into account the environmental information in accordance with regulation 4 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017f3, and, as national policy statements have effect in relation to the proposed development, has had regard to the documents and matters referred to in section 104(2) of the 2008 Act.

The Secretary of State is satisfied that the open space forming special category land specified in the land plan (onshore) and special category land plan (as defined in article 2 of this Order), when burdened with any new rights authorised to be compulsorily acquired under this Order, will be no less advantageous than it was before to the persons in whom it is vested, other persons, and the public, and that, accordingly, section 132(3) of the 2008 Act applies.

The Secretary of State, having decided the application, has determined to make an Order granting development consent for the development described in the application with modifications which in the opinion of the Secretary of State do not make any substantial changes to the proposals comprised in the application.

The Secretary of State, in exercise of the powers conferred by sections 114, 115, 120, 122, 123, 132, 140 and 149A and schedule 5 to the 2008 Act, makes the following Order:

Annotations to the whole text

Footnotes

f1

2008 c. 29. Section 37 was amended by section 128(2) and Schedule 13, Part 1, paragraphs 1 to 5 of the Localism Act 2011 (c. 20).

f2

S.I. 2010/103. This instrument was amended by S.I. 2012/635.

f3

S.I. 2017/572.

Contents

  1. Part 1: Preliminary
  2. 1Citation and commencement
  3. 2Interpretation
  4. Part 2: Principal Powers
  5. 3Development consent etc. granted by the Order
  6. 4Operation of generating station
  7. 5Deemed marine licence under the 2009 Act
  8. 6Power to maintain the authorised project
  9. 7Benefit of the Order
  10. 8Application and modification of legislative provisions
  11. 9Defence to proceedings in respect of statutory nuisance
  12. Part 3: Streets
  13. 10Street works
  14. 11Application of the 1991 Act
  15. 12Temporary restriction of use of streets
  16. 13Temporary closure of public rights of way
  17. 14Access to works
  18. 15Agreements with street authorities
  19. Part 4: Supplemental powers
  20. 16Discharge of water
  21. 17Authority to survey and investigate the land
  22. 18Protective work to buildings
  23. Part 5: Powers of acquisition
  24. 19Compulsory acquisition of land
  25. 20Time limit for exercise of authority to acquire land compulsorily
  26. 21Compulsory acquisition of rights
  27. 22Compulsory acquisition of land: minerals
  28. 23Private rights
  29. 24Application of the 1981 Act
  30. 25Acquisition of subsoil only
  31. 26Modification of Part 1 of the 1965 Act
  32. 27Rights under or over streets
  33. 28Temporary use of land for carrying out the authorised project
  34. 29Temporary use of land for maintaining the authorised project
  35. 30Statutory undertakers
  36. 31Recovery of costs of new connections
  37. 32Funding
  38. Part 6: Miscellaneous and general
  39. 33Application of landlord and tenant law
  40. 34Felling or lopping of trees and removal of hedgerows
  41. 35Trees subject to tree preservation orders
  42. 36Abatement of works abandoned or decayed
  43. 37Saving provisions for Trinity House
  44. 38Crown rights
  45. 39Protective provisions
  46. 40Operational land for the purposes of the 1990 Act
  47. 41Certification of plans and documents, etc.
  48. 42Service of notices
  49. 43No double recovery
  50. 44Requirements, appeals, etc.
  51. 45Arbitration
  52. Signature
  53. Schedule 1: Authorised Project
  54. 1Authorised Development
  55. 1Paragraph 1
  56. Part 2: Ancillary Works
  57. 2Paragraph 2
  58. Schedule 2: Requirements
  59. 1Time limits
  60. 2Offshore design parameters
  61. 3Aviation safety
  62. 4Stages of authorised project
  63. 5Onshore Substation works
  64. 6Detailed design parameters onshore
  65. 7Provision of landscaping
  66. 8Implementation and maintenance of landscaping
  67. 9Code of construction practice
  68. 10Highway accesses
  69. 11Onshore archaeology
  70. 12Landscape and ecology management plan
  71. 13European protected species onshore
  72. 14Construction hours
  73. 15Restoration of land used temporarily for construction
  74. 16Control of operational artificial light emissions
  75. 17Control of noise during operational stage
  76. 18Operational drainage
  77. 19Skills and Employment plan
  78. 20Offshore decommissioning
  79. 21Onshore decommissioning
  80. 22Great Dun Fell, Lowther Hill and St. Anne’s Primary Surveillance Radar
  81. 23Warton Aerodrome Primary Surveillance Radar
  82. 24Air traffic services at Liverpool John Lennon Airport
  83. 25Operation of Blackpool Airport
  84. 26Air traffic services at Isle of Man Airport
  85. 27Operation of Walney Aerodrome (Air traffic services)
  86. 28Operation of Warton Aerodrome (Air traffic services)
  87. 29Wake effects
  88. 30Landscape enhancement scheme
  89. 31Requirement for written approval
  90. 32Amendments to approved details
  91. Schedule 3Streets subject to street works
  92. Schedule 4Streets to be temporarily closed or restricted
  93. Schedule 5Public rights of way to be temporarily closed or restricted
  94. Schedule 6Access to works
  95. Schedule 7Land of which only temporary possession may be taken
  96. Schedule 8Land in which only new rights etc. may be acquired
  97. Schedule 9: Modification of compensation and compulsory purchase enactments for creation of new rights and imposition of restrictions
  98. 1Compensation enactments
  99. 2Compensation enactments
  100. 3Compensation enactments
  101. 4Application of Part 1 of the 1965 Act
  102. 5Application of Part 1 of the 1965 Act
  103. Schedule 10: Protective provisions
  104. Part 1: Protection of electricity, gas, water and sewerage undertakers
  105. 1Paragraph 1
  106. 2Paragraph 2
  107. 3Paragraph 3
  108. 4Acquisition of land
  109. 5Removal of apparatus
  110. 6Facilities and rights for alternative apparatus
  111. 7Retained apparatus
  112. 8Expenses and costs
  113. 9Expenses and costs
  114. 10Miscellaneous
  115. 11Miscellaneous
  116. Part 2: Protection for operators of electronic communications code networks
  117. 12Paragraph 12
  118. 13Paragraph 13
  119. 14Paragraph 14
  120. 15Paragraph 15
  121. Part 3: For the protection of Dŵr Cymru Cyfyngedig (DC)
  122. 16Paragraph 16
  123. 17Paragraph 17
  124. 18Paragraph 18
  125. 19Precedence of the WIA 1991
  126. 20Protection of DC apparatus
  127. 21Suspension of works
  128. 22Co-Operation
  129. 23Emergency Works
  130. 24Damage to DC apparatus
  131. Part 4: For the protection of SP Manweb as electricity undertaker
  132. 25Application
  133. 26Interpretation
  134. 27On Street Apparatus
  135. 28Acquisition of land
  136. 29Removal of apparatus
  137. 30Facilities and rights for alternative apparatus
  138. 31Retained apparatus: Protection of SP Manweb as Electricity Undertaker
  139. 32Expenses
  140. 33Indemnity
  141. 34Enactments and agreements
  142. 35Co-operation
  143. 36Access
  144. 37Arbitration
  145. Part 5: For the protection of Wales and West Utilities
  146. 38Paragraph 38
  147. 39Paragraph 39
  148. 40On street apparatus and offshore works
  149. 41Apparatus in streets subject to temporary restriction
  150. 42Acquisition by agreement
  151. 43Removal of apparatus
  152. 44Facilities and rights for alternative apparatus
  153. 45Retained apparatus
  154. 46Expenses and costs
  155. 47Co-operation
  156. 48Enactments and agreements
  157. Part 6: For the protection of the Welsh Ministers as Strategic Highway Authority
  158. 49Application
  159. 50Interpretation
  160. 51Approvals
  161. 52Approvals
  162. 53Approvals
  163. 54Approvals
  164. 55Approvals
  165. 56Approvals
  166. 57Approvals
  167. 58Indemnity
  168. 59Indemnity
  169. 60Traffic management
  170. 61Traffic management
  171. 62Inspections
  172. 63Inspections
  173. 64Inspections
  174. 65Inspections
  175. 66Reinstatement
  176. 67Reinstatement
  177. 68Reinstatement
  178. 69Notice of completion of Works
  179. 70Notice of completion of Works
  180. 71Notice of completion of Works
  181. 72Notice of completion of Works
  182. 73Arbitration
  183. 74Notices
  184. 75Cease of Use or Abandonment
  185. 76Cease of Use or Abandonment
  186. 77Cease of Use or Abandonment
  187. 78Maintenance
  188. Part 7: For the protection of National Grid Electricity Transmission Plc as electricity undertaker
  189. 79Application
  190. 80Interpretation
  191. 81Interaction with the Bodelwyddan Project and the Connah’s Quay Project
  192. 82Mona project works
  193. 83Mona project works
  194. 84Mona project works
  195. 85Mona project works
  196. 86On Street Apparatus
  197. 87Apparatus in temporarily closed streets
  198. 88Protective works to buildings
  199. 89Acquisition of land
  200. 90Removal of apparatus
  201. 91Facilities and rights for alternative apparatus
  202. 92Retained apparatus: Protection of National Grid Electricity Transmission Plc as Electricity Undertaker
  203. 93Expenses
  204. 94Indemnity
  205. 95Enactments and agreements
  206. 96Co-operation
  207. 97Access
  208. 98Arbitration
  209. 99Notices
  210. Part 8: For the protection of Network Rail Limited
  211. 100Paragraph 100
  212. 101Paragraph 101
  213. 102Paragraph 102
  214. 103Paragraph 103
  215. 104Paragraph 104
  216. 105Paragraph 105
  217. 106Paragraph 106
  218. 107Paragraph 107
  219. 108Paragraph 108
  220. 109Paragraph 109
  221. 110Paragraph 110
  222. 111Paragraph 111
  223. 112Paragraph 112
  224. 113Paragraph 113
  225. 114Paragraph 114
  226. 115Paragraph 115
  227. 116Paragraph 116
  228. 117Paragraph 117
  229. 118Paragraph 118
  230. 119Paragraph 119
  231. Part 9: For the protection of Awel y Môr
  232. 120Paragraph 120
  233. 121Paragraph 121
  234. 122Paragraph 122
  235. 123Paragraph 123
  236. 124Paragraph 124
  237. 125Paragraph 125
  238. 126Paragraph 126
  239. 127Paragraph 127
  240. 128Paragraph 128
  241. 129Paragraph 129
  242. 130Paragraph 130
  243. 131Paragraph 131
  244. 132Paragraph 132
  245. 133Paragraph 133
  246. 134Paragraph 134
  247. 135Paragraph 135
  248. 136Paragraph 136
  249. Schedule 11: Removal of hedgerows
  250. 1Removal of hedgerows
  251. 2Removal of important hedgerows
  252. 3Trees subject to tree preservation orders
  253. Schedule 12: Approval of matters specified in requirements
  254. 1Interpretation
  255. 2Interpretation
  256. 3Applications made under requirements
  257. 4Further information
  258. 5Provision of information by Consultees
  259. 6Fees
  260. 7Appeal
  261. Schedule 13: Arbitration rules
  262. 1Primary objective
  263. 2Time periods
  264. 3Timetable
  265. 4Procedure
  266. 5Arbitrator’s powers
  267. 6Costs
  268. 7Confidentiality
  269. Schedule 14: Marine Licence ORML2429G: Mona Offshore Wind Farm Generation Assets
  270. Part 1: Licensed marine activities
  271. 1Interpretation
  272. 2Details of licensed marine activities
  273. 3Details of licensed marine activities
  274. 4Details of licensed marine activities
  275. 5Details of licensed marine activities
  276. 6Details of licensed marine activities
  277. 7Details of licensed marine activities
  278. 8Details of licensed marine activities
  279. Part 2: Conditions
  280. 9Design parameters
  281. 10Maintenance of the authorised scheme
  282. 11Extension of time periods
  283. 12Notifications and inspections
  284. 13Colouring of structures
  285. 14Aids to navigation
  286. 15Chemicals, drilling and debris
  287. 16Force majeure and dropped objects
  288. 17Pre-construction plans and documentation
  289. 18Pre-construction plans and documentation
  290. 19Underwater Sound Management Strategy
  291. 20Low order unexploded ordnance clearance
  292. 21Offshore safety management
  293. 22Reporting of engaged agents, contractors and vessels
  294. 23Pre-construction surveys
  295. 24Construction monitoring
  296. 25Post-construction monitoring
  297. 26Reporting of scour and cable protection
  298. 27Completion of construction
  299. 28Marine Noise Registry
  300. 29Requirement for written approval
  301. Schedule 15Documents to be certified
  302. Explanatory note