Paragraph 22 Great Dun Fell, Lowther Hill and St. Anne’s Primary Surveillance RadarI1
England and Wales
No part of any wind turbine generator (excluding foundations) shall be erected as part of the authorised development until a primary radar mitigation scheme agreed in advance with the operator has been submitted to and approved in writing by the Secretary of State in order to mitigate the impact of the authorised development on the primary radar of the operator located at Great Dun Fell, Lowther Hill and St. Anne’s and associated air traffic management operations.
No part of any wind turbine generator (excluding foundations) shall be erected until the approved primary radar mitigation scheme has been implemented and the authorised development shall thereafter be operated fully in accordance with the approved scheme.
In this requirement—
-
“operator” means NATS (En Route) plc, incorporated under the Companies Act 2006 (Company Number 4129273) whose registered office is 4000 Parkway, Whiteley, Fareham, Hampshire PO15 7FL or such other organisation licensed from time to time under sections 5 and 6 of the Transport Act 2000 to provide air traffic services to the relevant managed area (within the meaning of section 40 of the Transport Act 2000); and
-
“primary radar mitigation scheme” or “scheme” means a detailed scheme agreed with the operator which sets out the measures to be taken to mitigate the impact of the development on the primary radar located at Great Dun Fell, Lowther Hill and St Annes and air traffic management operations of the operator.
Annotations
Commencement
- I1
Sch. 2 para. 22 in force at 28.7.2025, see art. 1