Paragraph 126 I1

England and Wales

(1)

The undertaker must not under the powers of this Order carry out any specified works without the consent of Awel y Môr, which must not be unreasonably withheld or delayed but which may be made subject to reasonable conditions and if Awel y Môr does not respond within 56 days then consent is deemed to be given.

(2)

Subject to obtaining consent pursuant to sub-paragraph (1) and not less than 56 days before beginning to construct any specified works, the undertaker must submit plans of the specified works to Awel y Môr and must submit such further particulars available to it that Awel y Môr may reasonably require.

(3)

Any specified works must be constructed without unreasonable delay in accordance with the plans approved in writing by Awel y Môr.

(4)

Any approval of Awel y Môr required under this paragraph may be made subject to such reasonable conditions as may be required for the protection or alteration of any apparatus within the Overlap area or the Awel y Môr Onshore Works or for securing access to any apparatus within the Overlap area or the Awel y Môr Onshore Works.

(5)

Where Awel y Môr requires any protective works to be carried out either by themselves or by the undertaker (whether of a temporary or permanent nature) such protective works must be carried out to Awel y Môr’s reasonable satisfaction.

(6)

Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of any specified works, new plans instead of the plans previously submitted, and the provisions of this paragraph shall apply to and in respect of the new plans.

Annotations

Commencement

I1

Sch. 10 para. 126 in force at 28.7.2025, see art. 1