OpenLegislation

Paragraph 81 Interaction with the Bodelwyddan Project and the Connah’s Quay ProjectI1

England and Wales

Without limiting any other provision of this Part of this Schedule, the undertaker must use reasonable endeavours to avoid any conflict arising between the construction, maintenance and operation of the authorised development and the Bodelwyddan Project and the Connah’s Quay Project. For the purposes of this paragraph, “reasonable endeavours” means—

(a)

undertaking consultation on the detailed design and programming of the Mona project works and all works associated with or ancillary to the Mona project works to ensure that the design and programme for the Mona project works does not unreasonably impede or interfere with the Bodelwyddan Project and/or the Connah’s Quay Project;

(b)

having regard to the proposed programme of works for the Bodelwyddan Project and/or the Connah’s Quay Project as may be made available to the undertaker by National Grid and facilitating a co-ordinated approach to the programme, land assembly, and the carrying out of the Mona project works and the Bodelwyddan Project and/or the Connah’s Quay Project;

(c)

providing a point of contact for continuing liaison and co-ordination throughout the construction and operation of the authorised development; and

(d)

keeping National Grid informed on the programme of works for the authorised development.

Annotations

Commencement

I1

Sch. 10 para. 81 in force at 28.7.2025, see art. 1