Paragraph 98 ArbitrationI1
England and Wales
Save for differences or disputes arising under paragraphs 90(2), 90(4), 91(1) and 92 any difference or dispute arising between the undertaker and National Grid Electricity Transmission Plc under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and National Grid Electricity Transmission Plc, be determined by arbitration in accordance with article 45 (arbitration).
Annotations
Commencement
- I1
Sch. 10 para. 98 in force at 28.7.2025, see art. 1