Schedule 7 Land of which only temporary possession may be takenI1
England and Wales
In the County of Conwy:
| (1) Number of plot shown on land plan (onshore) | (2) Purpose for which temporary possession may be taken | (3) Relevant part of authorised project |
|---|---|---|
| 01-001, 01-002 | Access to Work No. 3 during construction | Work Nos. 3 and 4 |
| 01-003, 01-004, | Temporary construction compound for vehicle parking, a circulation area and a laydown area of up to 800 square metres including fencing together with access to Work No. 4 during construction | Work Nos. 4 and 7 |
| 01-005, 01-006, 01-007, 01-008, 01-009, 01-010, 01-011 | Access during construction | Work Nos. 5, 7 and 8 |
| 02-013, 02-013a, 02-014, 02-015, 02-016, 02-017, 02-018, 02-019, 02-020 | Access to Work No. 8 during construction | Work Nos. 6 and 8 |
| 02-030 | Access to Work No. 10 during construction including works to the public highway and visibility splays | Work Nos. 9 and 10 |
| 03-052, 03-055, 03-057, 03-058, 04-068, 04-069, 04-071, 04-076 | Access to Work No. 12 during construction | Work Nos. 12 and 12a |
| 05-094, 05-095, 06-099, 06-102, 06-104 | Temporary construction compounds and laydown areas with a total maximum area of 37,500 square metres and access to Work Nos. 12 and 14 during construction including works to the public highway and visibility splays | Work Nos. 12, 13 and 14 |
In the County of Denbighshire:
| (1) Number of plot shown on land plan (onshore) | (2) Purpose for which temporary possession may be taken | (3) Relevant part of authorised project |
|---|---|---|
| 09-160, 09-162, 09-163, 09-164, 09-165 | Temporary construction compound and laydown area of up to 22,500 square metres and access to Work No. 17 during construction including works to the public highway and visibility splays | Work Nos. 17 and 18 |
| 09-166, 09-167 | Temporary works to the public highway including visibility splays | Work No. 19 |
| 11-197a, 11-223b, 11-228, 11-229a, 11-230, 11-230a, 11-233, 11-233a, 11-233b, 11-234, 1-234a, 11-234b, 11-236 | Access during construction including works to the public highway and visibility splays | Work Nos. 22, 22a, 27, 28, 29 and 30 |
| 11-197b | Onshore site preparation works | Work No. 27 |
| 11-228, 11-229 | Temporary construction compound and laydown area of up to 7,100 square metres | Work Nos. 22, 22a, 27, 28, 29 and 30 |
| 11-221a | Temporary construction area to facilitate the construction of permanent access | Work Nos. 27 and 29 |
| 11-215, 11-218, 11-218a | Temporary landscaping, ecological and environmental works in relation to the substation construction | Work Nos. 22, 22a and 31 |
Annotations
Commencement
- I1
Sch. 7 in force at 28.7.2025, see art. 1