OpenLegislation

Paragraph 70 Notice of completion of WorksI1

England and Wales

The undertaker must supply the WM with as built records of any apparatus sited within or under the strategic highway within 10 working days of the completion of works, including, in particular, the location and depth of any electrical cables on a plan to a scale of 1/500 with a longitudinal and vertical accuracy of + or - 100mm.

Annotations

Commencement

I1

Sch. 10 para. 70 in force at 28.7.2025, see art. 1