Paragraph 11 Onshore archaeologyI1
England and Wales
No stage of the onshore works may commence until for that stage an onshore written scheme of investigation has been submitted to and approved in writing by the relevant planning authority.
The onshore written scheme of investigation must accord with the outline onshore written scheme of investigation as appropriate for the relevant stage.
The onshore written scheme of investigation must be implemented as approved.
Onshore site preparation works, including those necessary to allow production of any scheme required under sub-paragraph (1) must only take place in accordance the applicable details set out in the outline onshore written scheme of investigation.
Annotations
Commencement
- I1
Sch. 2 para. 11 in force at 28.7.2025, see art. 1