Paragraph 9 Air traffic services at Isle of Man AirportI1
England, Wales and Scotland
No part of any wind turbine generator (excluding foundations) shall be erected as part of the authorised development until the Secretary of State, having consulted with the operator and the Isle of Man Civil Aviation Administration, confirms that either—
no mitigation is required in respect of the authorised development; or
should mitigation be required in respect of the authorised development—
an appropriate mitigation scheme will be implemented and maintained for the lifetime of the authorised development; and
a mitigation agreement has been offered to the operator to ensure that the appropriate mitigation will be implemented.
For the purposes of this requirement—
“appropriate mitigation scheme” means a scheme agreed between the undertaker and the operator which sets out measures taken to prevent or remove any adverse impacts of the authorised development on the Isle of Man Primary Surveillance Radar and air traffic management operations and the operator’s ability to provide safe and efficient air traffic services for Isle of Man Airport during the life of the authorised development;
“approved mitigation” means an appropriate mitigation scheme approved in accordance with sub-paragraph (1)(b); and
“operator” means Isle of Man Airport or such other organisation as is licensed from time to time to provide air traffic services for Isle of Man Airport.
The undertaker shall thereafter comply with all obligations contained within the approved mitigation for the lifetime of the authorised development.