Paragraph 4 I1
Prior to 1st January 2029, no wind turbine generator or offshore substation platform shall be erected in the WTG and OSP aviation buffer zone unless otherwise agreed in writing between the owner and the undertaker.
Annotations
Commencement
- I1
Sch. 3 Pt. 2 para. 4 in force at 23.12.2025, see art. 1