OpenLegislation

Paragraph 4 I1

The undertaker must notify Stena Line at least 28 days prior to the commencement of any specified works that involve the installation of subsea cable circuits and subsea cable ducts, such written notice to include full details of the location of any subsea cable circuits and subsea cable ducts and any other apparatus, equipment or infrastructure that is to be inserted in the underwater environment.

Annotations

Commencement

I1

Sch. 3 Pt. 6 para. 4 in force at 23.12.2025, see art. 1