Paragraph 28 Construction monitoringI1

England and Wales

(1)

The undertaker must, in discharging condition 20(1)(c) for each stage of construction, submit details (which accord with the offshore in principle monitoring plan) for approval in writing by the MMO in consultation with the relevant statutory nature conservation bodies of any proposed monitoring, including methodologies and timings, to be carried out during the construction of the authorised scheme. The monitoring proposals must specify each monitoring proposal’s objectives and explain how it will assist in either informing a useful and valid comparison with the pre-construction position and/or will enable the validation or otherwise of key predictions in the environmental statement.

(2)

The construction monitoring must include—

(a)

marine traffic monitoring in accordance with the offshore in principle monitoring plan, including the provision of reports on the results of that monitoring at the end of each year of the construction period to the MMO, MCA and Trinity House;

(b)

in the event that driven or part-driven pile foundations are proposed, measurements of underwater sound generated by the installation of the first four piled foundations of each piled foundation type to be installed collectively under this licence and licence 2 unless the MMO otherwise agrees in writing; and

(c)

in the event that driven or part-driven pile foundations are proposed, measurements of underwater sound generated by the installation of the first two piled foundations where it is anticipated hammer energies greater than 3,000kJ may be required for installation, unless the MMO otherwise agrees in writing.

(3)

In the event that piled foundations are proposed to be used, the details submitted in accordance with the marine mammal mitigation protocol must include proposals for monitoring marine mammals.

(4)

The undertaker must carry out the monitoring approved under sub-paragraph (1), including any further underwater sound monitoring required in writing by the MMO, and provide the agreed reports in the agreed format in accordance with the agreed timetable, unless otherwise agreed in writing with the MMO in consultation with the relevant statutory nature conservation bodies.

(5)

The results of the initial underwater sound measurements monitored in accordance with sub-paragraph (2)(b) must be provided to the MMO within six weeks of the installation of the first four piled foundations. The assessment of this report by the MMO will determine whether any further underwater sound monitoring is required. If, in the reasonable opinion of the MMO in consultation with the relevant statutory nature conservation body, the assessment shows significantly different underwater sound modelling results to those assessed in the environmental statement or failures in mitigation, all piling activity must cease until an update to the marine mammal mitigation protocol and further monitoring requirements have been agreed.

(6)

The results of the any underwater sound measurements monitored in accordance with sub-paragraph (2)(c) must be provided to the MMO within six weeks of the installation of the first two piled foundations that exceed 3,000kJ of hammer energy. The assessment of this report by the MMO will determine whether any further underwater sound monitoring is required. If, in the reasonable opinion of the MMO in consultation with the relevant statutory nature conservation body, the assessment shows significantly different underwater sound modelling results to those assessed in the environmental statement or failures in mitigation, any piling activity where the hammer energy is anticipated to exceed 3,000kJ must cease until an update to the marine mammal mitigation protocol and further monitoring requirements have been agreed.

(7)

The undertaker must carry out the surveys specified in the offshore monitoring plan in accordance with that plan, including any further underwater sound monitoring required in writing by the MMO under sub-paragraph (4), unless otherwise agreed in writing by the MMO in consultation with the relevant statutory nature conservation body.