In the Districts of Mid-Suffolk, Babergh and Braintree In the Districts of Mid-Suffolk, Babergh and Braintree

England and Wales

Works as shown on Sheets 4, 5, 7 to 17 (inclusive), 19, 20, 21 and 22 of the work plans to allow the removal of 25 kilometres of the existing overhead distribution electric line (Route PCB) between Burstall Bridge at a point indicated as PCB5 and a point to the west of Twinstead Tee indicated as PCB89, including—

(a)

the modification of existing pylons PCB5 and PCB89;

(b)

the dismantling and removal of all overhead distribution electric line and pylons including foundations between Burstall Bridge commencing at a point indicated as PCB5 on Sheet 4 of the work plans (but not including pylon PCB5) and terminating at a point to the west of Twinstead Tee indicated as PCB89 on Sheet 22 of the work plans (but not including pylon PCB89); and

(c)

the dismantling and removal of conductors, insulators and fittings.

Notes on Schedule 1

Commencement

I1

Sch. 1 in force at 4.10.2024, see art. 1