OpenLegislation

Paragraph 4 I1

England and Wales

(1)

No stage of the authorised development may commence until, for that stage, the following plans as relevant to that stage, have been submitted to and approved by the relevant planning authority (in consultation with Natural England in the case of the landscape and ecological management plan) or other discharging authority as may be appropriate to the relevant plan concerned and in the case of the construction traffic management plan, the relevant highway authority. The relevant plans are—

(a)

A construction environmental management plan (which must be substantially in accordance with the outline construction environmental management plan);

(b)

A materials and waste management plan (which must be substantially in accordance with the outline materials and waste management plan);

(c)

A construction traffic management plan (which must be substantially in accordance with the outline construction traffic management plan);

(d)

A landscape and ecological management plan (which must be substantially in accordance with the outline landscape and ecological management plan); and

(e)

A public right of way management plan (which must be substantially in accordance with the outline public right of way management plan).

(2)

All construction works forming part of the authorised development must be carried out in accordance with the plans listed in paragraph (1), unless otherwise agreed with the relevant planning authority or other discharging authority as may be appropriate to the relevant plan concerned, and in the case of the construction traffic management plan, the relevant highway authority.

(3)

For the avoidance of doubt, all pre-commencement operations must be carried out in accordance with the outline construction environmental management plan, the outline materials F1and waste management plan, the outline construction traffic management plan, the outline landscape and ecological management plan and the outline public right of way management plan unless otherwise agreed with the relevant planning authority or other discharging authority as may be appropriate to the relevant plan concerned, and in the case of the F2construction traffic management plan, the relevant highway authority.

Annotations

Textual amendments

F1

Word in Sch. 3 para. 4(3) inserted (9.4.2025) by The National Grid (Bramford to Twinstead Reinforcement) (Correction) Order 2025 (S.I. 2025/475), art. 1, Sch. Table 1

F2

Words in Sch. 3 para. 4(3) substituted (9.4.2025) by The National Grid (Bramford to Twinstead Reinforcement) (Correction) Order 2025 (S.I. 2025/475), art. 1, Sch. Table 1

Commencement

I1

Sch. 3 para. 4 in force at 4.10.2024, see art. 1