OpenLegislation

Paragraph 3 I1

England and Wales

(1)

Unless otherwise agreed with the relevant planning authority, written notice setting out the anticipated programme for the carrying out of pre-commencement operations must be given to the relevant planning authority no less than seven days prior to the date on which those pre-commencement operations are first carried out.

(2)

The authorised development may not commence until a written scheme setting out all stages of the authorised development has been submitted to the relevant planning authority.

(3)

Any revisions to the written scheme referred to in sub-paragraph (2) above must be submitted to the relevant planning authority in advance of the commencement of the stage of the authorised development to which the revisions relate.

(4)

Written notice of the commencement and completion of construction of each stage of the authorised development, and the operational use of each stage of the authorised development, must be given to the relevant planning authority within ten business days of the relevant event occurring.

(5)

The authorised development must be carried out in accordance with the written scheme submitted further to sub-paragraph (2) or (3) and, to the extent applicable, in general accordance with the written notice submitted further to sub-paragraph (1).

Annotations

Commencement

I1

Sch. 3 para. 3 in force at 4.10.2024, see art. 1