Paragraph 43 Site Specific Mitigation Scheme
No stage of the authorised development that affects the sites listed below may commence until a site specific mitigation scheme to mitigate all the impacts of construction activities, including noise, dust, vibration, and visual effects, has been submitted to and approved in writing by the relevant local planning authority. The sites are—
Sunnydene, Northwick Road, Mark, Highbridge, TA9 4PG;
Moorland Park Hewish, Congresbury, BS24 6RQ;
Merriedown, Old Lane, Tickenham, Clevedon, BS21 6RZ;
Spindlewood, Cadbury Camp Lane, Clapton-in-Gordano, BS20 7SA;
Paragon Vehicle Services Limited’s Paint Shop on BPC land at Royal Portbury Wharf, Mainsite South, Royal Portbury Dock Road, Portbury, Bristol, BS20 7XJ;
St Anthony’s Park, Kings Weston Lane, Avonmouth, BS11 8AZ;
The construction works for the relevant stage of the authorised development must be carried out in accordance with the approved scheme referred to in sub-paragraph (1) above.