Paragraph 5 Interpretation of Schedule 4I1
England and Wales
(1)
In this Schedule—
-
“the appeal parties” means the relevant authority, the requirement consultee and the undertaker;
-
“relevant authority” means the relevant planning authority, highway authority, street authority, Environment Agency, the Marine Management Organisation, Natural England, relevant drainage authority or relevant owner of a watercourse, sewer or drain as may be appropriate to the consent or approval sought; and
-
“requirement consultee” means any body named in a Requirement which is the subject of an appeal as a body to be consulted by the relevant authority in discharging that Requirement.
Annotations
Commencement
- I1
Sch. 4 para. 5 in force at 24.8.2017, see art. 1